M-59 (Huron Road) closing within Woodward Loop in Pontiac until summer 2027 for utility work
News originally published by
Michigan Department of TransportationPONTIAC, Mich. - The Michigan Department of Transportation (MDOT) is partnering with Oakland County and the City of Pontiac to rebuild the Woodward Loop between I-75 Business Loop (BL), US-24 Business Route (BR) and M-59 to enhance the safety, connectivity and livability of the Pontiac area. The project will restore two-way traffic to the loop and create pedestrian and bicycle access to important regional assets, including the Clinton River Trail, the new Oakland County offices and the rail bus station.
Preliminary utility work will begin soon, requiring crews to close M-59 (Huron Street) within the Woodward Loop through summer 2027. The overall project is expected to be completed in fall 2029.
9 a.m. Monday, Nov. 30 - Summer 2027:
- Eastbound M-59 (Huron Street) will be closed at the Woodward Loop/Cass Avenue/Wide Track Drive. Detour: Southbound Woodward Loop to north on the Woodward Loop to eastbound M-59.
- Westbound M-59 (Huron Street) will be closed at the Woodward Loop/Woodward Avenue. Detour: Northbound Woodward Loop and around to westbound M-59.
This utility work will involve DTE relocating underground electrical infrastructure along M-59, connecting to existing manholes on adjacent city streets. Crews will also be installing about 3,000 feet of concrete-encased duct bank, building 17 new manholes and relocating existing electrical circuits from two substations.
By closing each direction of the road, DTE can complete this utility relocation work more efficiently, quickly and safely.
This $48 million project to rebuild 2.7 miles of the Woodward Loop between I-75 BL, US-24 BR and M-59 includes drainage improvements, replacing traffic signals, operational improvements, sidewalk improvements compliant with the Americans with Disabilities Act (ADA), lighting upgrades, and sign and pavement marking replacement.
A video on MDOT YouTube channel further explains the project's scope and goals.
Legal Disclaimer:
EIN Presswire provides this news content "as is" without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the author above.